Guangqi Honda Automobile Co., Ltd. (GHAC), an automobile production and sales joint venture of Honda in China, held a ceremony this week to commemorate the start of construction of a third production line and an engine plant within the property of its existing ZengCheng Plant. The ceremony was attended by dignitaries, guests and representatives from the local governments of Guangzhou, Guangdong Province as well as Honda executives including Takanobu Ito, president & CEO; and Seiji Kuraishi, chief operating officer for regional operations in China.
The third line will be an environmentally-responsible and energy-saving production line, including a solar power generation system with a 10,000 kilowatt-capacity, the largest* capacity solar power generation system installed by an automaker in China. The advanced and efficient production line will adopt a highly-functional painting technology which significantly reduces the number of painting processes, as well as a highly efficient laser welding machine for the stamping plant.
The third line is scheduled to become operational in 2015, with an initial annual production capacity of 120,000 units. GHAC is planning to further expand the capacity up to 240,000 units in the future. When the third line becomes operational in 2015, GHAC's overall annual automobile production capacity will be increased from the current 480,000 units to 600,000 units, increasing Honda's overall annual automobile production capacity in China from the current 870,000 units to 1.01 million units.
The total investment for the third line (with capacity expandable up to 240,000 units) and the new engine plant is expected to be approximately 3.56 billion R.M.B.(approximately 450 million euros).
By expanding production capacity in the dynamically growing automobile market in China, Honda will further strengthen its ability to deliver new products which focus on Chinese customers, with speed, affordability and low CO2 emissions.
* Honda internal research
Honda’s Annual Automobile Production Capacity in China
Plant/Line |
Current |
2015 |
||
Guangqi Honda |
HuangPu Plant |
No. 1 |
240,000 |
240,000 |
ZengCheng Plant |
No. 2 |
240,000 |
240,000 |
|
No. 3 |
- |
120,000 |
||
Subtotal |
480,000 |
600,000 |
||
Dongfeng Honda |
1st Plant |
240,000 |
240,000 |
|
2nd Plant |
100,000 |
120,000 |
||
Subtotal |
340,000 |
360,000 |
||
Honda Automobile (China) (export only) |
5,000 |
5,000 |
||
TOTAL |
870,000 |
1,010,000 |
About Guangqi Honda Automobile Co., Ltd.
Established: July 1998
Capital Investment: US$283.29 million
Capitalization Ratio: 50% Guangzhou Auto Group Corp.
40% Honda Motor Co., Ltd.
10% Honda Motor (China) Investment Co., Ltd.
Location: Guangzhou City, Guangdong Province, China
Representative: Toshiaki Mikoshiba, President
Employment: Approximately 7,600 associates